Friday, July 30, 2021
Wednesday, July 28, 2021
BULB CASTING
We were finally given the go-ahead to cast our lead bulbs. I scrapped out an old boat for our lead. We had our “mock bulb” pressed into a sand mixture, making a proper mold. We then borrowed an old furnace, and within several hours, had poured molten lead into 4 bulb molds. I had been worried for sometime about this job, but it went so easily, I was speechless. The next day we broke open the molds, cut off the risers (pour holes), and started cleaning up the bulbs. Currently they are 77kg, BUT they need to be drilled, bolt heads counter sunk, trimmed, and faired. THEN, I will bring the weight down to 72kg (the max allowed).
Bulb mold |
Glueing the top on |
Cold furnace |
Preparing to pour |
Almost finished lead bulb |
Sunday, July 25, 2021
DECK THE HULLS with
Now that the boat is right side up, a bunch more jobs can get done. First the cabin stringers went on (same process as the hull), then all the bulkheads and ring frames were faired flat (just like the hull), and deck beams were installed. Finally, the 9mm plywood deck was epoxied and screwed down (just like the hull) EXCEPT these areas are much smaller and I am more efficient since I have done this work three times.
With the deck down, it received the required layer of epoxy and cloth. Also, most of the interior was sanded, sealed with epoxy, and some of the bilge areas received primer and paint.
Deck Beams & Stringers Deck about to go down Deck down w/ hatch cutouts Aft water tight compartment in epoxy After compartment in primer Final paint Cockpit Sole Taped seams Cloth coated Cockpit combings Removing camber for deck hatches Side view Observation pod glued down Epoxy lined holes for all deck hardware Mast step question Mast step mold Mast wedge of strengthened epoxy
Saturday, July 3, 2021
ROOM AT THE MARK!
First ever 5.80 crash, then roll over…!
Well for the first time ever two 5.80s have traded paint. On the way out of the shop, hull 79 scraped hull 113. Good news that it was just primer. Once outside, the crane picked up and then rolled hull 79 right side up.
The boat at this point weighed 880 lbs (400 kg) according to the crane operator. I used furniture dollies to roll the strongback out, and the same dollies to roll the cradle back into the shop. From crane hook up to set down it was 32 minutes of fun, (but I had to rent the crane for four hours).
The next few pictures are the deck beams and cabin sides going together, all the jobs now are flying along and going well.
I adopted a donor boat, to harvest lead and a few more goodies. I stripped the boat as best as I could, then went to the shipyard to haul the boat out. I cut the boat up with a Sawzall (reciprocating saw). It was a lot of work, but did get 800 lbs (362.8 kg) of lead ingots from the keel. I’m bringing a new boat into the world, I took an old boat out of the world. I think far more boats are being built than being recycled, but that’s a different topic…
Scraping by hull 113 on the way out |
Donor boat getting smaller |